This week, cab and body interior content was being finalized after your apparatus completed generator and road testing. After any remaining detail work that may be required is completed, preparations to ready your apparatus for final inspection should begin. Download the whole report.
This is your last scheduled report.
Rescue Squad 49 - Construction Update - April 8th
This week additional work was completed inside the body. The air system and AC electrical systems were
also nearing completion. Next week the remainder of the body interior should near completion as well as
compartment interiors. The cab interior should be finalized as your apparatus heads to road and generator testing late next week.